登録して招待リンクを共有すると、動画再生報酬と紹介報酬を獲得できます。

Mike Baier
@Mike__Baier
Removing traffic from the world one tunnel at a time. Director of Production, Electrical, and Software Engineering at The Boring Company
参加 March 2020
762 フォロー中    7K ファン
On hard-rock machines like Prufrock Main beam, the propulsion system doesn’t push off a tunnel liner — because there is no liner. The rock itself forms the walls. Instead, Prufrock Main beams grip the tunnel walls with ~4 million pounds of horizontal force. Think of bracing yourself hard against both sides of a narrow hallway and then pushing forward. That’s the principle. By gripping the rock directly, we delete entire subsystems: no liners, no erectors, no segment handling, no grout. The result is counter-intuitive: the maximum theoretical tunneling speed through hard rock is significantly higher than through soft soil. Simpler machine. Faster progress
もっと見る