Tesla crews have set more than 30 Megapacks in a single day. This is how a grid-scale battery goes up.
At Giga Texas, Tesla is installing a 133 MW, 266 MWh Megapack project that provides backup power for the data center on site. Each unit rolls in on a flatbed from the Lathrop Megafactory, gets lifted by crane from six points, and drops onto pier foundations driven straight into the ground.
8 a day on this site. Over 30 in a day where the site and equipment allow it.