J.P. Morgan full double upgrade report on $IREN:
"We are upgrading IREN to Overweight. We see IREN establishing itself as a top tier neocloud provider, backed by its strategic partnership with NVIDIA.”
Customers and pricing:
“The company has gained momentum in signing customers and industry pricing has moved up substantially. Neocloud contracts have gone from $10-15/W to $15-20/W and higher today depending on delivery, GPU generation, and contract duration.”
Customer pre-payments:
“Customer pre-payments, which help fund GPU procurement, have ranged from 25-50% and we expect pre-payments to remain a part of future neolcoud deals.”
ARR:
“IREN has increased its calendar year-end 2026 expected ARR from $3.4b last November to $3.7b in May of this year and, most recently, up to $4.0b. The company has $1b in operating ARR today and delivered the first (Horizon 1) of four 50 MW buildings (200 MW total; capacity as IT unless noted) under the contract with Microsoft. Horizon 2-4 (150 MW total) are expected to be delivered by the end of calendar 2026.”
Customer base:
“The company’s largest contract announcements are with Microsoft and Nvidia, but an unnamed recent signing is a multi-year contract with a leading frontier AI lab. IREN has also signed deals with Prometheus, Figure AI, Perplexity, Together AI, Fluidstack, Hume AI, Fireworks AI, Fal AI, Higgsfield, and Cohere.”
JPM believes the ~0.5 GW expansion in 2027 could be signed at materially higher prices:
“While the company has laid out its plans to spend $25-30b of capex in FY27, along with substantial increases in opex, we believe the company’s ~0.5 GW expansion in 2027 could be signed at materially higher prices than past deals in the $12-15/W range. Any contracts above $15/W would be highly accretive to financials.”
Near term risks:
“We do see some near-term risks for the 2027 pipeline, derived from the current audit on data center interconnection requests in Texas. If the audit and verification process persists beyond the mid-terms in November, projects could see delays in development timelines. As a positive development, IREN last week announced Sweetwater 1 and 2 had both been conditionally included in ERCOT’s Batch Zero process as Base Load. We move to an Overweight rating and establish a Dec-27 PT of $65 (vs. a Dec-26 PT of $46 prior)."