16 September 2026 Giga Texas VIDEO … Beautiful day to fly and to see the very active End-of-Line (EOL and outbound lots today.
Many Cybertruck, Cybercabs, Model Y/YLs and test track activity with a long single group of Cybercabs racing around the large oval while Model YL’s test out on the inner oval.
The W side near Tesla Rd, the large clearing has more Geotextile membranes installed and addition prep work ahead of construction start. Nearby, in the new staging lot, transformers were being set up.
N Campus Optimus Factory steel assembly continues to progress rapidly, including more concrete work on the upper 3 floors. The Advanced Tech Chip Fab is getting a large section of the ground slap poured with concrete.
Cortex 2 is getting work on the N extension while the W side Megapack installation seems to be paused, Much more to see today!