注册并分享邀请链接,可获得视频播放与邀请奖励。

Wall St Engine
@wallstengine
Fast, accurate, consistent stock market news, earnings highlights & more. By Brillinsight. Not financial advice.
加入 March 2022
972 正在关注    196.4K 粉丝
ORACLE SEEKS PROTECTION FROM DATA CENTER DELAYS $ORCL has issued a force majeure notice tied to Project Jupiter, the 2.45GW New Mexico data center that is part of the Stargate AI buildout, Bloomberg reports. Oracle is not trying to exit the project, but is seeking to delay payments if the site misses its planned 2028 opening. The project has faced permitting setbacks, including a six-month delay to a key gas pipeline. Its $18B construction debt is already trading below 90 cents on the dollar. Oracle says the project remains on schedule.
显示更多
0
37
441
64
转发到社区