14 October 2026 Giga Texas VIDEO … Pre-dawn flight today to capture more of the site in the dark, highlighting just how much activity there is with both regular production (employees were arriving for their shift start) & construction, which is pretty much 24/7 on the site.
At the Optimus factory we get great views inside the structure that is now ~40% assembled! The main steel assembly may be complete within 6 months!
On the E side of the main factory, the Vertical Reciprocating Conveyor system has some of the mechanicals & one of the red loading/elevator lifts installed.
Over at the W side of the highway, the large lot that has been graded near Tesla Rd is getting a large section paved with asphalt.
Finally, just S of the EOL facility, 3 banks for new superchargers is making fast progress!