SpaceX $SPCX gave a more specific Terrafab roadmap on its Q3 call.
Musk’s internal target is a functional test chip around May–June 2027 at the Austin research fab. He described an SRAM-type chip used to test the production line, not a finished AI processor.
For the main Terrafab site at Gibbons Creek, he initially targeted volume production around Q3 2028, then described Q3 or Q4 2028 as possible outcomes.
He called those dates extremely aggressive and stressed the large uncertainties around achieving them.
On equipment, Musk thanked ASML $ASML and other suppliers for accelerating deliveries. But the analyst’s specific question about EUV machine orders and delivery timing did not receive an explicit answer. No EUV order quantity, model or delivery date was confirmed in that exchange.
The longer-term ambition is much larger: Musk said Terrafab ultimately aims to produce a terawatt of AI chips per year. He did not provide a date for that goal.
The milestones are distinct: an Austin test chip first, then volume manufacturing at Gibbons Creek. Late-2028 production remains an aspiration,