DOE has offered Grid United up to $2.8B to build a 106-mile line tying the Eastern and Western grids together in Wyoming
The Wyoming Intertie adds about 1.8 GW of transfer capacity, doubling what can move between SPP and WECC today.
It runs between substations near Medicine Bow and Wheatland and uses HVDC back-to-back converters to link the two unsynchronized systems.
DOE estimates up to $39B in savings across 17 states over 30 years of operation. It has not published the method behind that figure.
Grid United CEO Michael Skelly started Grain Belt Express at Clean Line Energy. DOE terminated Grain Belt's $4.9B loan guarantee last year.
The commitment is conditional, and the line is scheduled to finish in 2033.