今晚是 $IREN 的财报,貌似还没跌到底!😂
新云这波真的是杀得狠,融资压力越来越大,现在又碰上数据中心审批风险。接下来会不会有一轮行业洗牌,甚至出现更多并购?
Texas froze new data center grid hookups back in august. and tuesday's surprise midterm result likely makes that freeze last longer.
ERCOT runs the texas grid, and big power users wait in its queue to get connected.
that queue is ~474GW (of which ~90% data centers) today
ERCOT paused new data center hookups and delayed its first big study batch during an audit due dec 10.
governor-elect hinojosa (takes office jan 19) has promised a ban on all data center approvals until lawmakers pass new rules.
so it's quite likely that most new texas projects in 2028 get delayed, with some demand moving to other states.
most exposed - these are some big Texas sites waiting for approval:
- $IREN has a 2GW Sweetwater hub, with 300MW targeted for Q4 2027.
- Cipher: a 1GW site, Colchis, targeted for 2028, plus several more sites still under study (SEC deck)
- Hut 8 and CleanSpark: a 1GW site, Beacon Point, plus Sealy and Brazoria
顯示更多