Semiconductor equipment subsystem lead times:
Deposition-equipment component lead times ~4 → up to 10 months.
Laser-process Japanese parts up to 40 months, no premium pulls them forward.
Packaging-tool components lead times up +~50%. Fab tool deliveries ~2×. Drag already flagged on Samsung Pyeongtaek and SK Yongin.