Register and share your invite link to earn from video plays and referrals.

Dan Nystedt
@dnystedt
Former journalist, now financial analyst. Based in Taipei. Tweet mainly about semiconductors and Taiwan. Not investment advice. Views are my own.
Joined June 2009
1.2K Following    54.9K Followers
TSMC will begin 1.4nm (A14) trial production in the 1st quarter next year, media report, and equipment is already being moved-in to Hsinchu’s Fab 20 (P3). TSMC’s Fab 25 in Taichung, central Taiwan, will be the second 1.4nm fab, with phase 1 construction to finish in April, and trial production to begin as early as the 3rd quarter-2027. Taichung will be the main A14 cluster. The A14 timeline is ahead of schedule, something TSMC had noted during its 2nd quarter earnings call in July. $TSM #semiconductors#
Show more