Options Trader & Growth Investor Advanced Market Research (Not Financial Advice)
Joined August 2021
341 Following    44.5K Followers
Bitcoin miners are sitting on 32GW of planned power, most of it is still unspoken for $IREN: 5.8GW planned, 540MW contracted $CIFR: 4.03GW planned, 700MW contracted $HUT: 3.97GW planned, 1.33GW contracted $WULF: 3.63GW planned, 1GW contracted $MARA: 2.75GW planned, 0 contracted $CORZ: 2.55GW planned, 1.5GW contracted $RIOT: 2GW planned, 318MW contracted $CLSK: 1.83GW planned, 250MW contracted $GLXY: 1.7GW planned, 800MW contracted $BITF: 771MW planned, 0 contracted